Title
Park Avenue Bridge Replacement Project - Notice of Completion for Contract No. 6155 (15R20)
Recommendation
a) Approve an additional construction contract change amendment for John S. Meek Company, Inc. in the amount of $231,788.98 (3.7% of the original contract) to cover the additional construction costs beyond the original 10 percent contingency;
b) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. A Mitigated Negative Declaration (MND) was adopted by the City Council on November 24, 2014;
c) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and
d) Release Faithful Performance Bond one (1) year after acceptance by the City Council.