Title
OASIS Senior Center Site Lighting Phase 2 - Award of Contract No. 9009-3 (26F02)
Recommendation
a) Find this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(a), Class 1 (Interior or exterior alterations involving such things as interior partitions, plumbing, and electrical conveyances) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project has no potential to have a significant effect on the environment;
b) Approve the project plans and specifications;
c) Declare SFADIA Inc., dba Green Innovations Inc. bid non-responsive due to performing less than 50% of the work listed on the submitted bid per section 2-3.2 Self Performance of the Public Works Standard Specifications;
d) Relieve Optima Energy Inc. of its bid due to a bid error;
e) Approve Budget Amendment No. 26-017 appropriating $149,950 in new revenue and expenditures from the U.S. Department of Energy to 13501-980000-26F02;
f) Award Contract No. 9009-3 to SacTown Contractors Corporation for the total bid price of $526,450 for the OASIS Senior Center Site Lighting Phase 2 project, and authorize the Mayor and City Clerk to execute the contract; and
g) Establish a contingency of $53,000 (approximately 10% of total bid) to cover the cost of unforeseen work not included in the original contract.